Permit Details

Permit Search

Permit

Mobile Home

174 SW COUNTY ROAD 242A
LAKE CITY, FL 32025

Permit #
000044236
Application #
54331
Status Completed
  1. Submitted Apr 11, 2022
  2. Issued Apr 21, 2022
  3. Expires Jan 30, 2023
  4. Completed Aug 3, 2022

Property

Parcel #
08815-000
Owner
Strickland Brent Mathew
Acres
1.75
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0401C
In floodway
N
Mobile Home is a:
Single Wide
Year Built
1984
Width (Ft.In)
14
Length (Ft.In)
66
Driveway access to home:
Existing Drive
Installation Decal #
88591
Septic #
22-0324
Setbacks Front
30'
Setback Side 1
25'
Setbacks Rear
25'
Dev Permit #
F023-
Setback Side 2
25'
Are you applying for a 5 year temporary permit?
No
Serial #
SSM-FLA-C-11-2200
Wind Zone?
2
Residential or Commercial Use?
Residential
Service Amps
200

Status & Review History

  1. Application pending.
  2. City of Lake City Utilities Notified
  3. City of Lake City
  4. Point Review - Printed-Online Application
  5. Point Review - Reviewed
  6. Plan Review - Reviewed
  7. Zoning Review - Reviewed
  8. Zoning Review - Reviewed
  9. Final Review - Documents Required
  10. Final Review - Reviewed
  11. Final Review - Payment Needed
  12. Permit Issued

Contractors

  • Brent M Strickland

    License
    IH1104218
    Title
    Mh Installer (ih)
    Role
    Contractor

Inspections

  1. Apr 19, 2022

    Passed: Mobile Home - In County Pre-Mobile Home before set-up

    Inspected by Troy Crews

  2. Apr 21, 2022

    Septic Release Inspection

    Inspected by Health Dept

  3. Aug 2, 2022

    Failed: Mobile Home - Mobile Home Set-Up Final

    Not Complete Steps Hookup Etc.

    Inspected by Troy Crews

  4. Aug 2, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Aug 3, 2022

    Passed: Mobile Home - Mobile Home Set-Up Final

    Inspected by Troy Crews

  6. Aug 3, 2022

    Release to power company

    Inspected by Troy Crews

  7. Aug 3, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews