Permit Details

Permit Search

Permit

New Commercial Construction

3157 NW YORK DR
LAKE CITY, FL 32055

Permit #
000044177
Application #
53786
Status Completed
  1. Submitted Mar 4, 2022
  2. Issued Apr 14, 2022
  3. Expires Mar 31, 2024
  4. Completed Oct 4, 2023

Property

Parcel #
02556-003
Owner
Notami Hospitals Of Fl Inc
Acres
41.25
Subdivision
—
Zoning
—
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a:
13,800 SF Prefabricated Metal Building
Driveway access to property:
Existing Drive
Is there a Fire Sprinkler System?
Yes
Setbacks Front
20'
Setback Side 1
10'
Setback Side 2
10'
Setback Rear
15'
Describe commercial use:
Lake City Medical Center - Hospital
Stories
1
Heated Area (Sqft)
13800
Total Area (Sqft)
13800
Building Height
19
Building Code Construction Type
II
Building Code Element
B
Building Code Occupancy Types
Storage
Occupancy Use Title
B (Business) and A-3 (Assembly)
Dev Permit #
F023-
Design Occupant Load
355
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
x-city
Sealed roof decking options. (Must select one.)
Other (explain)
Sealed roof decking explanation for other option.
part of building
Service Amps
2111.25

Status & Review History

  1. Application pending.
  2. City of Lake City
  3. Plan Review - Documents Required
  4. Point Review - Documents Required
  5. Plan Review - Documents Required
  6. Point Review - Documents Required
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Plan Review - Documents Required
  11. Plan Review - Plumbing Approved
  12. Plan Review - Mechanical Approved
  13. Plan Review - Electrical Approved
  14. Plan Review - Building Approved
  15. Plan Review - Building Approved
  16. Plan Review - Reviewed
  17. Zoning Review - Reviewed
  18. Final Review - Documents Required
  19. Final Review - Documents Required
  20. Final Review - Documents Required
  21. Final Review - Payment Needed
  22. Permit Issued

Contractors

  • Thomas Smith

    W.w. Gay Mechanical Contractor Of Gainesville Inc

    License
    CMC1249841
    Title
    Mechanical Contractor
    Role
    Subcontractor
  • Thomas Smith

    W.w. Gay Mechanical Contractor Of Gainesville Inc

    License
    CFC1425962
    Title
    Plumbing Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Robert Gambrell

    Robins & Morton

    License
    CGC057104
    Title
    Cert. General
    Role
    Contractor

    County License & State License Expired.

  • Joni Wilford

    Scherer Construction Of North Florida

    License
    CCC1327794
    Title
    Cert. Roofing
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Richard Bloom

    W W Gay Gay Fire Protection, Inc.

    License
    421788-0001-2001
    Title
    Cert. Fire/water System
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

  • James B Seay

    Miller Electric Company

    License
    EC13003061
    Title
    Cert. Electrical
    Role
    Subcontractor

Inspections

  1. Sep 7, 2022

    Passed: Building - Footer

    Partial Retaining Wall Foundation Southwest Corner

    Inspected by Troy Crews

  2. Sep 7, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Sep 16, 2022

    Passed: Building - Footer

    First Pour Wall

    Inspected by Troy Crews

  4. Sep 16, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Sep 21, 2022

    Passed: Building - Footer

    Partial Retaining And Building Footer.

    Inspected by Troy Crews

  6. Sep 21, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  7. Oct 4, 2022

    Passed: Building - Footer

    Wall Pour

    Inspected by Troy Crews

  8. Oct 4, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  9. Oct 13, 2022

    Passed: Building - Footer

    Inspected by Troy Crews

  10. Oct 13, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  11. Oct 24, 2022

    Passed: Building - Footer

    Partial Loading Dock And Partial Back Wall

    Inspected by Troy Crews

  12. Oct 24, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  13. Nov 2, 2022

    Passed: Building - Footer

    Northwest Corner And Partial North End

    Inspected by Troy Crews

  14. Nov 2, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  15. Nov 9, 2022

    Passed: Fire - Plan Review

    Inspected by Dwight Boozer

  16. Dec 1, 2022

    Passed: Building - Footer

    Inspected by Troy Crews

  17. Dec 1, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  18. Dec 21, 2022

    Passed: Building - Footer

    Inspected by Troy Crews

  19. Dec 21, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  20. Dec 29, 2022

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Waste Lines Ancilliary Building

    Inspected by Troy Crews

  21. Jan 3, 2023

    Passed: Building - Vertical Cells/Columns

    Inspected by Troy Crews

  22. Jan 4, 2023

    Passed: Electrical - 1st Underground Rough–In

    Underground Strapped Off To Driven Unistrut

    Inspected by Troy Crews

  23. Jan 5, 2023

    Passed: Building - Footer

    Inspected by Troy Crews

  24. Jan 5, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  25. Jan 11, 2023

    Passed: Building - Footer

    Column Pads

    Inspected by Troy Crews

  26. Jan 11, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  27. Jan 11, 2023

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  28. Jan 17, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  29. Jan 24, 2023

    Passed: Building - Slab

    Main Building Slab

    Inspected by Troy Crews

  30. Jan 27, 2023

    Passed: Building - Footer

    Inspected by Troy Crews

  31. Jan 27, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  32. Feb 14, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Storm Drain Rough In

    Inspected by Troy Crews

  33. Feb 22, 2023

    Passed: Building - Slab

    Inspected by Troy Crews

  34. Feb 28, 2023

    Cancelled: Mechanical - Rough In

    Inspected by Troy Crews

  35. Feb 28, 2023

    Passed: Plumbing/Gas - Rain Leader

    Reminder Of Rain Leaders For Ancillary Building

    Inspected by Troy Crews

  36. Feb 28, 2023

    Passed: Plumbing/Gas - Sanitary

    Main Copper Water Line Pressure Test Of 160

    Inspected by Troy Crews

  37. Mar 9, 2023

    Passed: Building - Framing

    Also Window Frames

    Inspected by Troy Crews

  38. Mar 9, 2023

    Cancelled: Building - Rated Assembly Fastening

    Inspected by Troy Crews

  39. Mar 16, 2023

    Passed: Building - Slab

    Inspected by Troy Crews

  40. Mar 29, 2023

    Failed: Building - Masonry Wall Reinforcing

    Already Poured Send Third Party Approval

    Inspected by Troy Crews

  41. Mar 29, 2023

    Failed: Building - Vertical Cells/Columns

    Inspected by Troy Crews

  42. Mar 31, 2023

    Passed: Building - Slab

    Inspected by Troy Crews

  43. Apr 5, 2023

    Failed: Building - Framing

    Not Ready Framing Has Been Moved To Cut Floor.

    Inspected by Troy Crews

  44. Apr 5, 2023

    Failed: Electrical - 2nd Rough-In

    Not Ready Floor Cut New Conduits Going In.

    Inspected by Troy Crews

  45. Apr 19, 2023

    Passed: Mechanical - Rough In

    Main Ducts For Air Handlers.

    Inspected by Troy Crews

  46. Apr 24, 2023

    Passed: Electrical - 2nd Rough-In

    Partial Hallway North End

    Inspected by Troy Crews

  47. Apr 24, 2023

    Passed: Mechanical - Framing/Fire Damper

    Inspected by Troy Crews

  48. Apr 24, 2023

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  49. Apr 24, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Need To Stub Out Condensate Drain

    Inspected by Troy Crews

  50. Apr 26, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    50 Psi Test.

    Inspected by Troy Crews

  51. Apr 27, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  52. Apr 27, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Two Areas Still Need Water Line Test

    Inspected by Troy Crews

  53. May 2, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  54. May 5, 2023

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  55. May 5, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  56. May 12, 2023

    Passed: Mechanical - Rough In

    Partial Supply Ducts

    Inspected by Anthony Aslan

  57. May 25, 2023

    Rescheduled 5/26/2023:Mechanical - Rough In

    Inspected by Troy Crews

  58. May 26, 2023

    Passed: Mechanical - Rough In

    Superintendent Signed Off Pressure Test On 5-25-23

    Inspected by Anthony Aslan

  59. Jun 13, 2023

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  60. Jun 13, 2023

    Release to power company

    Inspected by Troy Crews

  61. Jun 29, 2023

    Passed: Building - Fire Rated Wall

    Inspected by Troy Crews

  62. Jun 29, 2023

    Passed: Electrical - Above Ceiling

    Inspected by Troy Crews

  63. Jul 7, 2023

    Passed: Building - Final

    Ok To Stock And Prep. Pending Fire Dept. Approval

    Inspected by Troy Crews

  64. Oct 2, 2023

    Passed: Building - Final

    Co Pending Fire Insp. And Panel Schedules

    Inspected by Troy Crews

  65. Oct 3, 2023

    Passed: Fire - Fire Final

    Add Knox Box And Remove Electric Key Pad Lock On Riser Room Door

    Inspected by Joshua Wehinger

  66. Oct 4, 2023

    Certificate-Release Certificate

    Panels Labeled And Fire Final Done

    Inspected by Troy Crews

Documents