Permit Details

Permit Search

Permit

New Residential Construction

388 SW JEWEL LAKE DR
LAKE CITY, FL 32024

Permit #
000044067
Application #
53630
Status Completed
  1. Submitted Feb 22, 2022
  2. Issued Mar 31, 2022
  3. Expires Dec 9, 2023
  4. Completed Jun 12, 2023

Property

Parcel #
02439-227
Owner
Wjhfl Llc, D/b/a Wjh Llc,
Acres
0.23
Subdivision
Reserve At Jewel Lake Phase 2
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
124.50'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0290D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
1607
Total Area (Sqft)
2101
Building Height
17
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
x-city
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. City of Lake City
  3. City of Lake City
  4. City of Lake City
  5. City of Lake City
  6. Point Review - Printed-Online Application
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Zoning Review - Reviewed
  11. Final Review - Reviewed
  12. Final Review - Payment Needed
  13. Plan Review - Plumbing Approved
  14. Plan Review - Mechanical Approved
  15. Plan Review - Electrical Approved
  16. Plan Review - Building Approved
  17. Final Review - Payment Needed
  18. Permit Issued
  19. Final Review - Payment Needed
  20. Zoning Review - Reviewed
  21. Final Review - Payment Needed

Contractors

  • Morey Doyle

    Wade Jurney Homes Dba Wjhfl Llc

    License
    CGC1517458
    Title
    Cert. General
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Timothy D Shatto

    Shatto Heating & Air, Inc.

    License
    CAC057875
    Title
    A/c Class B
    Role
    Subcontractor
  • Ryan C Beville

    Rbi Electrical Contracting Llc

    License
    EC13004236
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Phillip M Mcdonald

    Phillip Mcdonald Plumbing Inc

    License
    CFC1428926
    Title
    Cert. Plumbing
    Role
    Subcontractor
  • Benjamin T Keeler

    Keeler Roofing, Llc

    License
    CCC1330509
    Title
    Cert. Roofing
    Role
    Subcontractor

Inspections

  1. Sep 7, 2022

    Cancelled: Building - Footer

    Inspected by Melissa Garber

  2. Sep 8, 2022

    Passed: Engineering - Setbacks

    Surveyor To Do Final Confirmation

    Inspected by Troy Crews

  3. Jan 20, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  4. Jan 26, 2023

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  5. Jan 26, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Feb 23, 2023

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  7. Feb 23, 2023

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Feb 23, 2023

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  9. Mar 23, 2023

    Passed: Building - Framing

    Inspected by Troy Crews

  10. Mar 23, 2023

    Failed: Electrical - 2nd Rough-In

    Need To Wire Bath Fans In Call Back In With Insulation

    Inspected by Troy Crews

  11. Mar 23, 2023

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  12. Mar 23, 2023

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Troy Crews

  13. Mar 30, 2023

    Passed: Building - Insulation

    Inspected by Troy Crews

  14. Mar 30, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  15. May 17, 2023

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  16. May 17, 2023

    Release to power company

    Inspected by Troy Crews

  17. Jun 7, 2023

    Failed: Building - Final

    Bath Fans Not Working, Water Heater Needs Pan And Drain, Need Ladder Onsite To Confirm Attic Insulation.

    Inspected by Troy Crews

  18. Jun 12, 2023

    Passed: Building - Final

    Items Corrected.

    Inspected by Troy Crews

  19. Jun 12, 2023

    Cancelled: Building - Final

    Inspected by Troy Crews

Documents