| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
3/29/2022 |
| Release to power company |
|
Matt Forsyth |
3/29/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
4/7/2022 |
| Passed: Building - Monolithic Slab |
|
Matt Forsyth |
4/14/2022 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
4/14/2022 |
| Passed: Electrical - 1st Underground Rough–In |
|
Matt Forsyth |
4/14/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
5/16/2022 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
5/16/2022 |
| Passed: Building - Framing |
|
Matt Forsyth |
5/26/2022 |
| Failed: Electrical - 2nd Rough-In |
Missing Smoke Detector In Hall |
Matt Forsyth |
5/26/2022 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
5/26/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
5/26/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
5/31/2022 |
| Passed: Building - Insulation |
|
Matt Forsyth |
6/1/2022 |
| Failed: Electrical - Permanent Power |
Conduit Needs To Be Run From Metercan To Power Pole. To Be Able To Release Power Need Septic Released |
Matt Forsyth |
6/24/2022 |
| Septic Release Inspection |
|
Health Dept |
6/27/2022 |
| Cancelled: Electrical - Permanent Power |
|
Emaleigh Williams |
6/30/2022 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
7/1/2022 |
| Release to power company |
|
Matt Forsyth |
7/1/2022 |
| Failed: Building - Final |
Outdoor Receptacles Have No Ground Fault Protection Need To Be Properly Labeled Impanel |
Matt Forsyth |
8/31/2022 |
| Passed: Building - Final |
Items Were Addressed |
Matt Forsyth |
9/1/2022 |