Permit Details

Permit Search

Permit

New Residential Construction

533 SW HOMESTEAD CIR
FORT WHITE, FL 32038

Permit #
000043872
Application #
53356
Status Completed
  1. Submitted Feb 2, 2022
  2. Issued Mar 8, 2022
  3. Expires Nov 12, 2023
  4. Completed May 23, 2023

Property

Parcel #
03818-110
Owner
Green Sheldon Wayne, Green Michele Marie
Acres
4.01
Subdivision
Old Wire Farms
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
82.90'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0480C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
2
Heated Area (Sqft)
800
Total Area (Sqft)
1040
Building Height
18
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
21-0881
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Point Review - Received-Hard Copy Application
  2. Zoning Review - Reviewed
  3. Plan Review - Plumbing Approved
  4. Plan Review - Mechanical Approved
  5. Plan Review - Electrical Approved
  6. Plan Review - Building Approved
  7. Plan Review - Reviewed
  8. Zoning Review - Reviewed
  9. Final Review - Documents Required
  10. Final Review - Documents Required
  11. Final Review - Reviewed
  12. Final Review - Payment Needed
  13. Permit Issued
  14. Final Review - Payment Needed

Contractors

This is an owner-builder project.

Inspections

  1. Feb 4, 2022

    Passed: Electrical - Temporary Service

    Inspected by Matt Forsyth

  2. Feb 4, 2022

    Release to power company

    Inspected by Matt Forsyth

  3. Mar 1, 2022

    Septic Release Inspection

    Inspected by Health Dept

  4. Apr 6, 2022

    Passed: Building - Footer

    Floor Framing 8 Anchors Each Side

    Inspected by Troy Crews

  5. Apr 6, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Apr 14, 2022

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  7. Apr 18, 2022

    Cancelled: Building - Footer

    Inspected by Anthony Aslan

  8. Apr 18, 2022

    Cancelled: Engineering - Setbacks

    Inspected by Anthony Aslan

  9. Apr 18, 2022

    Cancelled: Building - Masonry Wall Reinforcing

    Inspected by Anthony Aslan

  10. Apr 18, 2022

    Cancelled: Building - Monolithic Slab

    Inspected by Anthony Aslan

  11. Apr 18, 2022

    Cancelled: Building - Slab

    Inspected by Anthony Aslan

  12. May 26, 2022

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  13. May 26, 2022

    Release to power company

    Inspected by Anthony Aslan

  14. May 26, 2022

    Cancelled: Electrical - 1st Underground Rough–In

    Inspected by Anthony Aslan

  15. May 26, 2022

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  16. May 26, 2022

    Failed: Plumbing/Gas - 1st Underground Rough–In

    No Water On Second Floor Water Test Not Able To Verified, Have Question About Pipe Stub Out For Laundry

    Inspected by Anthony Aslan

  17. Jun 3, 2022

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Under Water

    Inspected by Anthony Aslan

  18. Apr 19, 2023

    Passed: Building - Insulation

    Recv'd Letter From Insulation Company

    Inspected by Anthony Aslan

  19. May 16, 2023

    Passed: Electrical - Permanent Power

    Inspected by Anthony Aslan

  20. May 16, 2023

    Release to power company

    Inspected by Anthony Aslan

  21. May 16, 2023

    Passed: Building - Final

    Doc's Recv'd-- Co Will Not Be Issued Until Assessments Are Recieved

    Inspected by Anthony Aslan

  22. May 17, 2023

    Cancelled: Building - Pre-Certificate Public Works Inspection

    Inspected by Anthony Aslan

  23. May 23, 2023

    Certificate-Release Certificate

    Inspected by Anthony Aslan