Permit Details

Permit Search

Permit

New Residential Construction

807 SW MANDIBA DR
LAKE CITY, FL 32024

Permit #
000043605
Application #
52819
Status Completed
  1. Submitted Jan 5, 2022
  2. Issued Jan 28, 2022
  3. Expires Mar 14, 2023
  4. Completed Sep 15, 2022

Property

Parcel #
09280-126
Owner
Rex And Karen Mitchell
Acres
1.04
Subdivision
Oaks Of Lake City Phase 1
Zoning
PRRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
86'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0395C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2061
Total Area (Sqft)
2887
Building Height
22
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
21-0198
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof.

Status & Review History

  1. Application pending.
  2. Point Review - Printed-Online Application
  3. Plan Review - Corrections Needed
  4. Plan Review - Building Approved
  5. Plan Review - Electrical Approved
  6. Plan Review - Mechanical Approved
  7. Plan Review - Plumbing Approved
  8. Plan Review - Reviewed
  9. Zoning Review - Reviewed
  10. Final Review - Reviewed
  11. Final Review - Payment Needed
  12. Permit Issued
  13. Permit reissued to reflect updated information.
  14. Permit reissued to reflect updated information.
  15. Final Review - Payment Needed
  16. Final Review - Payment Needed

Contractors

  • Anthony R Franks

    Franks & Lane Heating And Air Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Robert Ogles

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

    County License & State License Expired.

  • Donald R Hollingsworth

    Holly Electric Inc

    License
    EC13005429
    Title
    Electrical
    Role
    Subcontractor
  • Bryan Zecher

    Bryan Zecher Construction Inc

    License
    CBC054575
    Title
    Cert.building Contractor
    Role
    Contractor

Inspections

  1. Feb 2, 2022

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Feb 2, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Mar 17, 2022

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  4. Apr 4, 2022

    Passed: Building - Slab

    Inspected by Troy Crews

  5. Apr 18, 2022

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  6. Apr 18, 2022

    Release to power company

    Inspected by Troy Crews

  7. May 12, 2022

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. May 12, 2022

    Passed: Building - Framing

    Inspected by Troy Crews

  9. May 12, 2022

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  10. May 12, 2022

    Passed: Building - Strapping

    Inspected by Troy Crews

  11. May 12, 2022

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  12. Jun 3, 2022

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  13. Jun 3, 2022

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. Jun 3, 2022

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  15. Jun 7, 2022

    Passed: Building - Insulation

    Inspected by Troy Crews

  16. Jun 24, 2022

    Septic Release Inspection

    Inspected by Health Dept

  17. Aug 1, 2022

    Passed: Electrical - Permanent Power

    Need Drive Final

    Inspected by Troy Crews

  18. Aug 15, 2022

    Release to power company

    Inspected by Melissa Garber

  19. Sep 15, 2022

    Passed: Building - Final

    Inspected by Troy Crews

Documents