| Passed: Building - Footer |
|
Troy Crews |
1/27/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
1/27/2022 |
| Passed: Plumbing/Gas - Sanitary |
|
Anthony Aslan |
2/22/2022 |
| Passed: Building - Slab |
|
Troy Crews |
3/4/2022 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
5/26/2022 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
5/26/2022 |
| Passed: Building - Framing |
|
Troy Crews |
6/8/2022 |
| Septic Release Inspection |
|
Health Dept |
6/15/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
7/22/2022 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
7/22/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
7/22/2022 |
| Passed: Building - Insulation |
|
Troy Crews |
8/10/2022 |
| Cancelled: Electrical - Temporary Service |
|
Troy Crews |
9/21/2022 |
| Passed: Electrical - Permanent Power |
Septic Received |
Troy Crews |
2/21/2023 |
| Release to power company |
|
Troy Crews |
2/21/2023 |
| Passed: Building - Final |
Need Termite Final For Release. |
Troy Crews |
3/17/2023 |
| Certificate-Release Certificate |
Final Termite Received |
Troy Crews |
3/23/2023 |