| Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
1/27/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
1/27/2022 |
| Cancelled: Building - Footer |
|
Anthony Aslan |
2/3/2022 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
2/3/2022 |
| Passed: Building - Slab |
|
Anthony Aslan |
2/3/2022 |
| Failed: Building - Ext Strapping/Wall Sheathing |
No Exterior Strapping, Post Missing On Back Porch, |
Anthony Aslan |
2/25/2022 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
2/25/2022 |
| Passed: Building - Wall Sheathing |
Window Bottom Front Garage Missing Nails |
Anthony Aslan |
2/25/2022 |
| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
2/28/2022 |
| Release to power company |
|
Anthony Aslan |
2/28/2022 |
| Passed: Building - Framing |
Check At Insulation Electric Service, Top Plate Notch 50% Needs Cts218 Tension Strapping |
Anthony Aslan |
3/23/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
3/23/2022 |
| Passed: Mechanical - Rough In |
Check At Insulation For Gasket On All Supply And Returns |
Anthony Aslan |
3/23/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
3/23/2022 |
| Passed: Building - Insulation |
Correction Made On Pervious Notes |
Anthony Aslan |
5/10/2022 |
| Passed: Electrical - Permanent Power |
Need Picture Of Master Bath Vanity Wire Safety Off, Need Septic Release |
Anthony Aslan |
6/16/2022 |
| Septic Release Inspection |
|
Health Dept |
6/17/2022 |
| Release to power company |
Received Picture |
Anthony Aslan |
6/27/2022 |
| Cancelled: Building - Final |
|
Emaleigh Williams |
9/19/2022 |
| Passed: Building - Final |
|
Anthony Aslan |
9/19/2022 |