Additions
Permit
| Application #: | 52062 |
| Permit #: |
000043336 |
| Related Permit: |
|
| Submitted: | Thursday, October 28, 2021 |
| Issued: | Wednesday, December 8, 2021 |
| Expires: | Tuesday, August 2, 2022 |
| Completed: | Tuesday, August 2, 2022 |
| Status: |
Completed |
| Septic Release? |
Yes |
Job Details
| Finished floor requirement |
|
| Fema map number |
12023C0186D |
| Description of addition: |
carport/porch addition |
| Select driveway access to property: |
Existing Drive |
| Fire sprinklers? |
No |
| Setbacks Front |
30 |
| Setback Side 1 |
25 |
| Setback Side 2 |
25 |
| Setback Rear |
25 |
| Stories |
1 |
| Heated Area (Sqft) |
584 |
| Total Area (Sqft) |
1556 |
| Total Estimated Cost |
85000 |
| Building Height |
16 |
| Building Code Construction Type |
V |
| Building Code Element |
B |
| Building Code Occupancy Types |
Residential |
| Occupancy Use Title |
single family |
| Dev Permit # |
F023- |
| Building Code Edition |
2020 Florida Building Code 7th Edition and 2017 National Electrical Code |
| Septic# |
21-0894 |
| Is this an addition for commercial or residential use? |
Residential |
| Sealed roof decking options. (Must select one.) |
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof. |
Review Notes
| 10/11/2021 |
Application pending. |
| 10/29/2021 |
Point Review - Printed-Online Application |
| 11/5/2021 |
Zoning Review - Reviewed |
| 11/10/2021 |
Plan Review - Plumbing Approved |
| 11/10/2021 |
Plan Review - Mechanical Approved |
| 11/10/2021 |
Plan Review - Electrical Approved |
| 11/10/2021 |
Plan Review - Building Approved |
| 11/10/2021 |
Plan Review - Reviewed |
| 11/10/2021 |
Zoning Review - Reviewed |
| 11/10/2021 |
Final Review - Reviewed |
| 11/10/2021 |
Final Review - Payment Needed |
| 12/6/2021 |
Final Review - Payment Needed |
| 12/8/2021 |
Permit Issued |
Contractors
| Name / Business |
License |
Title |
Role |
Anthony R Franks Franks & Lane Heating And Air Llc
|
CAC1818631 |
Cert. A/c Class “b” |
Subcontractor |
Marcus Matthews Matthews Electric Llc
|
EC13005459 |
Electrical Contractor |
Subcontractor |
Cody Barrs Barrs Plumbing Inc
|
CFC1427145 |
Plumbing Contractor |
Subcontractor |
Robert Ogles Ogles Roofing & Construction Llc
|
CCC1328699 |
Cert Roofing |
Subcontractor |
Bryan Zecher Bryan Zecher Homes Inc
|
CBC1257343 |
Building Contractor |
Contractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Septic Release Inspection |
|
Health Dept |
11/2/2021 |
| Passed: Building - Monolithic Slab |
|
Matt Forsyth |
3/9/2022 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
3/9/2022 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
4/14/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
4/14/2022 |
| Passed: Building - Framing |
|
Matt Forsyth |
4/14/2022 |
| Passed: Building - Strapping |
|
Matt Forsyth |
4/14/2022 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
4/14/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
4/21/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
4/21/2022 |
| Passed: Building - Final |
|
Matt Forsyth |
8/2/2022 |