Permit Details

Permit Search

Permit

New Residential Construction

148 SW AMESBURY CT
LAKE CITY, FL 32024

Permit #
000043314
Application #
50232
Status Completed
  1. Submitted Nov 1, 2021
  2. Issued Dec 6, 2021
  3. Expires Nov 21, 2022
  4. Completed May 25, 2022

Property

Parcel #
03099-107
Owner
Cornerstone Developers Ii Llc
Acres
0.48
Subdivision
Stonehenge Phase 1
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0293D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
1534
Total Area (Sqft)
2305
Building Height
18
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
SINGLE FAMILY DWELLING
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
21-0828
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.

Status & Review History

  1. Point Review - Received-Hard Copy Application
  2. Final Review - Documents Required
  3. Zoning Review - Reviewed
  4. Plan Review - Plumbing Approved
  5. Plan Review - Mechanical Approved
  6. Plan Review - Electrical Approved
  7. Plan Review - Building Approved
  8. Plan Review - Reviewed
  9. Final Review - Documents Required
  10. Final Review - Documents Required
  11. Final Review - Documents Required
  12. Final Review - Payment Needed
  13. Permit Issued
  14. Final Review - Payment Needed

Contractors

  • Jerry Castagna

    Castagna Construction Inc

    License
    CBC047842
    Title
    Building Contractor
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Derrick L Williams

    Dl Williams Heating & Cooling Llc

    License
    CAC1816913
    Title
    Class "b" A/c Contractor
    Role
    Subcontractor
  • Frank Soucinek

    Dependable Plumbing

    License
    CFC057747
    Title
    Plumbing Contractor
    Role
    Subcontractor

    County License & State License & Workers Comp & Employees Workers Comp Expired.

  • Darin L Summerlin

    Summerlin Roofing Inc

    License
    CCC1326192
    Title
    Roofing Contractor
    Role
    Subcontractor

Inspections

  1. Dec 8, 2021

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Need Compaction Test-rec'd 12.9.21

    Inspected by Matt Forsyth

  2. Dec 13, 2021

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  3. Dec 13, 2021

    Release to power company

    Inspected by Troy Crews

  4. Dec 14, 2021

    Passed: Building - Monolithic Slab

    Inspected by Matt Forsyth

  5. Dec 14, 2021

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  6. Feb 10, 2022

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. Feb 10, 2022

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  8. Mar 1, 2022

    Passed: Building - Framing

    Inspected by Troy Crews

  9. Mar 1, 2022

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  10. Mar 1, 2022

    Failed: Mechanical - Rough In

    Main Return Not Complete, Need Nail Plate At Dryer Duct.

    Inspected by Troy Crews

  11. Mar 1, 2022

    Failed: Plumbing/Gas - 2nd Rough-In

    No Pressure On Water Lines

    Inspected by Troy Crews

  12. Mar 4, 2022

    Failed: Building - Insulation

    Mechanical And Plumbing Not Passed Yet

    Inspected by Troy Crews

  13. Apr 29, 2022

    Failed: Electrical - Permanent Power

    Need Culvert Final, Need Septic Final, Need Insulation Certification Letter From Insulation Contractor Certifying Insulation Since It Was Not Inspected.

    Inspected by Troy Crews

  14. May 3, 2022

    Passed: Electrical - Permanent Power

    Need Septic Final

    Inspected by Troy Crews

  15. May 3, 2022

    Release to power company

    Inspected by Troy Crews

  16. May 3, 2022

    Passed: Building - Insulation

    Letter On File

    Inspected by Troy Crews

  17. May 3, 2022

    Passed: Mechanical - Rough In

    Items

    Inspected by Troy Crews

  18. May 3, 2022

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  19. May 4, 2022

    Septic Release Inspection

    Inspected by Health Dept

  20. May 24, 2022

    Failed: Building - Final

    Need Blower Door Test, Water Heater Wired In, Disconnect On Power Supply At Air Handler.

    Inspected by Troy Crews

  21. May 25, 2022

    Passed: Building - Final

    Items Corrected, Blower Door Received

    Inspected by Troy Crews

Documents