Permit Details

Permit Search

Permit

New Residential Construction

225 SW PINEHURST DR
LAKE CITY, FL 32024

Permit #
000043010
Application #
51558
Status Completed
  1. Submitted Oct 13, 2021
  2. Issued Oct 22, 2021
  3. Expires Oct 8, 2023
  4. Completed May 2, 2023

Property

Parcel #
03087-104
Owner
Entrust Holdings Llc
Acres
0.71
Subdivision
Forest Country Sixth Addition
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
103.4'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0289D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
25
Setback Side 1
10
Setback Side 2
10
Setbacks Rear
15
Stories
1
Heated Area (Sqft)
2499
Total Area (Sqft)
3300
Building Height
21
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
21-0762
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.

Status & Review History

  1. Point Review - Received-Hard Copy Application
  2. Zoning Review - Reviewed
  3. Plan Review - Documents Required
  4. Plan Review - Documents Required
  5. Plan Review - Plumbing Approved
  6. Plan Review - Mechanical Approved
  7. Plan Review - Electrical Approved
  8. Plan Review - Building Approved
  9. Plan Review - Reviewed
  10. Zoning Review - Reviewed
  11. Final Review - Documents Required
  12. Permit Issued
  13. Final Review - Payment Needed

Contractors

  • Frank A Todd Iii(mike)

    Mike Todd Construction Inc

    License
    CGC006209
    Title
    General Contractor
    Role
    Contractor
  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Don C Bills Sr

    Hometown Plumbing Services Llc

    License
    CFC1428890
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Derrick L Williams

    Dl Williams Heating & Cooling Llc

    License
    CAC1816913
    Title
    Class "b" A/c Contractor
    Role
    Subcontractor

Inspections

  1. Jan 19, 2022

    Cancelled: Building - Footer

    Inspected by Troy Crews

  2. Jan 19, 2022

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jan 19, 2022

    Cancelled: Electrical - Temporary Service

    Inspected by Troy Crews

  4. Jan 20, 2022

    Passed: Building - Footer

    Inspected by Matt Forsyth

  5. Jan 20, 2022

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  6. Mar 2, 2022

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  7. Mar 9, 2022

    Passed: Building - Slab

    Fibermesh Concrete

    Inspected by Matt Forsyth

  8. Jul 5, 2022

    Passed: Building - Masonry Wall Reinforcing

    This Inspection Was For Ext Walls Contractor Working To Get Elevation Certificate

    Inspected by Matt Forsyth

  9. Aug 25, 2022

    Passed: Electrical - 1st Underground Rough–In

    Inspection Was For Second Rough Electric

    Inspected by Matt Forsyth

  10. Aug 25, 2022

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  11. Sep 1, 2022

    Passed: Building - Insulation

    Need Mechanical Before Cover Up

    Inspected by Matt Forsyth

  12. Sep 22, 2022

    Failed: Mechanical - Rough In

    This Project Is Missing Several Inspections Wall Sheathing Roof Sheathing Framing Inspection Those Need To Be Completed Before Moving Forward On Any Work Other Than Completing These Inspections

    Inspected by Matt Forsyth

  13. Sep 26, 2022

    Cancelled: Building - Wall Sheathing

    Inspected by Matt Forsyth

  14. Sep 26, 2022

    Cancelled: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  15. Sep 26, 2022

    Passed: Building - Strapping

    Inspected by Matt Forsyth

  16. Sep 26, 2022

    Passed: Building - Framing

    Inspected by Matt Forsyth

  17. Sep 26, 2022

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  18. Sep 26, 2022

    Cancelled: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  19. Sep 26, 2022

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  20. Jan 6, 2023

    Cancelled: Electrical - Permanent Power

    Inspected by Matt Forsyth

  21. Jan 9, 2023

    Passed: Electrical - Permanent Power

    Need And Septic And Driveway

    Inspected by Matt Forsyth

  22. Feb 20, 2023

    Septic Release Inspection

    Inspected by Health Dept

  23. Feb 23, 2023

    Release to power company

    Inspected by Melissa Garber

  24. Mar 2, 2023

    Release to power company

    Inspected by Melissa Garber

  25. Apr 11, 2023

    Passed: Building - Final

    Need Bdt And Final Termite

    Inspected by Matt Forsyth

  26. May 2, 2023

    Certificate-Release Certificate

    Inspected by Matt Forsyth

Documents