| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
10/27/2021 |
| Release to power company |
|
Matt Forsyth |
10/27/2021 |
| Passed: Building - Footer |
|
Troy Crews |
11/16/2021 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
11/16/2021 |
| Passed: Electrical - 1st Underground Rough–In |
|
Matt Forsyth |
12/30/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
12/30/2021 |
| Passed: Building - Slab |
Need Perimeter Bar On Porch |
Matt Forsyth |
1/4/2022 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
2/15/2022 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
2/15/2022 |
| Failed: Building - Framing |
Windows In Parts Of House Need To Be Tempered Glass |
Matt Forsyth |
3/30/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
5/24/2022 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
5/24/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
5/24/2022 |
| Passed: Building - Insulation |
|
Matt Forsyth |
6/9/2022 |
| Passed: Electrical - Permanent Power |
Need Septic Release |
Matt Forsyth |
8/23/2022 |
| Release to power company |
|
Melissa Garber |
8/25/2022 |
| Septic Release Inspection |
|
Health Dept |
8/25/2022 |
| Passed: Building - Final |
All Items Have Been Addressed |
Matt Forsyth |
10/27/2022 |