| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
8/18/2021 |
| Release to power company |
|
Matt Forsyth |
8/18/2021 |
| Cancelled: Electrical - Temporary Service |
|
Troy Crews |
8/18/2021 |
| Passed: Building - Footer |
|
Troy Crews |
1/11/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
1/11/2022 |
| Passed: Building - Lintel/Tie Beam |
Stem Walls |
Troy Crews |
6/9/2022 |
| Passed: Building - Masonry Wall Reinforcing |
|
Troy Crews |
6/9/2022 |
| Passed: Building - Framing |
Floor Framing |
Troy Crews |
11/23/2022 |
| Cancelled: Building - Slab |
|
Troy Crews |
11/23/2022 |
| Passed: Building - Framing |
|
Troy Crews |
4/3/2023 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
4/3/2023 |
| Passed: Building - Roof Decking |
|
Troy Crews |
4/19/2023 |
| Passed: Building - Rated Assembly Fastening |
|
Troy Crews |
10/2/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
3/8/2024 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
3/8/2024 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
3/8/2024 |
| Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
6/27/2024 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
6/27/2024 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
10/7/2024 |
| Passed: Building - Insulation |
|
Troy Crews |
10/7/2024 |
| Septic Release Inspection |
|
Health Dept |
10/7/2024 |
| Release to power company |
|
Troy Crews |
10/8/2024 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
3/19/2025 |
| Certificate-Release Certificate |
|
Troy Crews |
3/21/2025 |
| Passed: Building - Final |
|
Troy Crews |
3/21/2025 |