| Passed: Engineering - Setbacks |
|
Anthony Aslan |
8/17/2021 |
| Passed: Building - Footer |
|
Anthony Aslan |
8/17/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
9/24/2021 |
| Passed: Building - Monolithic Slab |
|
Anthony Aslan |
9/28/2021 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
9/28/2021 |
| Passed: Building - Slab |
|
Anthony Aslan |
9/28/2021 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
11/18/2021 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
11/18/2021 |
| Passed: Building - Framing |
|
Anthony Aslan |
12/17/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
12/17/2021 |
| Failed: Mechanical - Rough In |
Kitchen Hood No Screws In Seams
dryer Vent More Than 50% Of Bearing Top Plate Notched Needs Cts218 Tension Strap |
Anthony Aslan |
12/17/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
12/17/2021 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
12/20/2021 |
| Passed: Building - Insulation |
|
Anthony Aslan |
1/5/2022 |
| Septic Release Inspection |
|
Health Dept |
3/10/2022 |
| Passed: Electrical - Permanent Power |
|
Anthony Aslan |
3/11/2022 |
| Release to power company |
|
Anthony Aslan |
3/11/2022 |
| Passed: Building - Final |
Back Of Air Handler Needs To Be Sealed |
Anthony Aslan |
5/17/2022 |