| Passed: Building - Footer |
|
Matt Forsyth |
8/11/2021 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
8/11/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
9/16/2021 |
| Passed: Building - Slab |
|
Matt Forsyth |
9/24/2021 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
9/27/2021 |
| Release to power company |
|
Matt Forsyth |
9/27/2021 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
11/23/2021 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
12/15/2021 |
| Passed: Building - Framing |
|
Matt Forsyth |
12/15/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
1/28/2022 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
1/28/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
1/28/2022 |
| Septic Release Inspection |
|
Health Dept |
4/21/2022 |
| Passed: Building - Insulation |
|
Matt Forsyth |
5/4/2022 |
| Passed: Electrical - Permanent Power |
Driveway Release |
Matt Forsyth |
5/4/2022 |
| Release to power company |
|
Melissa Garber |
5/10/2022 |
| Cancelled: Building - Final |
|
Emaleigh Williams |
6/16/2022 |
| Cancelled: Building - Final |
|
Emaleigh Williams |
6/16/2022 |
| Passed: Building - Final |
Fresh Air Verified |
Matt Forsyth |
6/17/2022 |