| Passed: Engineering - Setbacks |
|
Anthony Aslan |
6/10/2021 |
| Passed: Building - Footer |
Need Picture Of Grounding Wire Installed, No Porta Potty. |
Anthony Aslan |
6/10/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
7/6/2021 |
| Failed: Building - Slab |
No Termite Treatment Paperwork On Site |
Matt Forsyth |
7/19/2021 |
| Passed: Building - Slab |
|
Matt Forsyth |
7/21/2021 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
9/2/2021 |
| Release to power company |
|
Matt Forsyth |
9/2/2021 |
| Cancelled: Building - Wall Sheathing |
|
Matt Forsyth |
9/3/2021 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
9/3/2021 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
9/3/2021 |
| Passed: Building - Framing |
|
Matt Forsyth |
10/4/2021 |
| Passed: Building - Strapping |
|
Matt Forsyth |
10/4/2021 |
| Passed: Electrical - 1st Underground Rough–In |
Second Rough Electrical Inspection |
Matt Forsyth |
10/4/2021 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
10/4/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
10/4/2021 |
| Passed: Building - Insulation |
Foam In Attic |
Anthony Aslan |
10/6/2021 |
| Passed: Electrical - Permanent Power |
Need Septic Release |
Matt Forsyth |
1/5/2022 |
| Release to power company |
|
Melissa Garber |
1/21/2022 |
| Septic Release Inspection |
|
Health Dept |
1/21/2022 |
| Passed: Building - Final |
|
Matt Forsyth |
3/3/2022 |