| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
6/21/2021 |
| Release to power company |
|
Matt Forsyth |
6/21/2021 |
| Passed: Building - Footer |
|
Matt Forsyth |
7/28/2021 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
7/28/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
8/11/2021 |
| Passed: Building - Slab |
Fibermesh Concrete |
Matt Forsyth |
8/13/2021 |
| Cancelled: Building - Slab |
|
Matt Forsyth |
8/16/2021 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
9/1/2021 |
| Rescheduled 9/2/2021:Building - Roof Decking |
|
Matt Forsyth |
9/1/2021 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
9/2/2021 |
| Passed: Building - Framing |
|
Matt Forsyth |
10/6/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
10/6/2021 |
| Passed: Mechanical - Rough In |
Two Boots Missing In Bedroom In Bath Will Check On Insulation Inspection |
Matt Forsyth |
10/6/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
10/6/2021 |
| Passed: Building - Insulation |
|
Troy Crews |
10/14/2021 |
| Release to power company |
|
Laurie Hodson |
11/19/2021 |
| Passed: Electrical - Permanent Power |
Need Septic Final |
Troy Crews |
11/19/2021 |
| Septic Release Inspection |
|
Health Dept |
11/19/2021 |
| Failed: Building - Final |
Need To Replace Receptacle On Front Porch |
Matt Forsyth |
12/2/2021 |
| Passed: Building - Final |
|
Matt Forsyth |
12/2/2021 |