| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
6/2/2021 |
| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
6/2/2021 |
| Release to power company |
|
Anthony Aslan |
6/2/2021 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
6/8/2021 |
| Passed: Building - Monolithic Slab |
Need Grounding Wire |
Anthony Aslan |
6/8/2021 |
| Release to power company |
Duke Energy States To Owner Theu Never Rec'd Temp. Power
release. |
Anthony Aslan |
7/8/2021 |
| Rescheduled 4/20/2022:Building - Wall Sheathing |
|
Anthony Aslan |
4/20/2022 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
4/20/2022 |
| Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Anthony Aslan |
4/20/2022 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
5/4/2022 |
| Passed: Building - Framing |
|
Anthony Aslan |
5/4/2022 |
| Passed: Building - Fire Rated Wall |
|
Anthony Aslan |
5/23/2022 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
5/23/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
5/23/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
5/23/2022 |
| Passed: Building - Insulation |
|
Anthony Aslan |
5/23/2022 |
| Passed: Electrical - Permanent Power |
Wires In Kitchens Need Safety Off |
Anthony Aslan |
6/29/2022 |
| Release to power company |
|
Anthony Aslan |
6/29/2022 |
| Passed: Building - Final |
Gfic Left Unit Porch Not Reseting |
Anthony Aslan |
8/24/2022 |