| Septic Release Inspection |
|
Health Dept |
4/19/2021 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
5/14/2021 |
| Passed: Building - Footer |
|
Anthony Aslan |
5/14/2021 |
| Passed: Building - Framing |
Partial Go Ahead And Pour Concrete. |
Troy Crews |
12/23/2021 |
| Passed: Building - Roof Decking |
Check Missed Nailing |
Anthony Aslan |
4/21/2022 |
| Cancelled: Building - Monolithic Slab |
|
Emaleigh Williams |
5/18/2022 |
| Cancelled: Engineering - Setbacks |
|
Emaleigh Williams |
5/18/2022 |
| Passed: Building - Monolithic Slab |
|
Anthony Aslan |
5/27/2022 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
5/27/2022 |
| Cancelled: Building - Monolithic Slab |
|
Anthony Aslan |
5/27/2022 |
| Cancelled: Engineering - Setbacks |
|
Anthony Aslan |
5/27/2022 |
| Passed: Building - Final |
|
Anthony Aslan |
8/29/2022 |