| Passed: Building - Footer |
|
Matt Forsyth |
4/20/2021 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
4/20/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
5/5/2021 |
| Passed: Building - Slab |
|
Matt Forsyth |
5/10/2021 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
7/22/2021 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
7/22/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
7/29/2021 |
| Passed: Building - Framing |
|
Matt Forsyth |
8/3/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
8/9/2021 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
8/9/2021 |
| Passed: Building - Insulation |
|
Matt Forsyth |
8/12/2021 |
| Septic Release Inspection |
|
Health Dept |
10/27/2021 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
11/10/2021 |
| Release to power company |
|
Matt Forsyth |
11/10/2021 |
| Passed: Building - Final |
Need Locking Caps Condenser, Blower Door Test |
Anthony Aslan |
11/16/2021 |
| Certificate-Release Certificate |
|
Anthony Aslan |
11/22/2021 |