Permit Details

Permit Search

Permit

New Residential Construction

397 SW KYLE WAY
LAKE CITY, FL 32025

Permit #
000041734
Application #
48788
Status Completed
  1. Submitted Mar 23, 2021
  2. Issued Apr 14, 2021
  3. Expires Aug 30, 2022
  4. Completed Mar 15, 2022

Property

Parcel #
09411-113
Owner
Primosch, Thomas F & Martha
Acres
1.01
Subdivision
Sweetgum Estates Part Of Lot
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0415C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setbacks Rear
25
Stories
1
Heated Area (Sqft)
1098
Total Area (Sqft)
2737
Building Height
20
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
21-0186

Status & Review History

  1. Application pending.
  2. Point Review - Printed-Online Application
  3. Zoning Review - Reviewed
  4. Plan Review - Documents Required
  5. Plan Review - Reviewed
  6. Zoning Review - Reviewed
  7. Final Review - Payment Needed
  8. Permit Issued
  9. Final Review - Payment Needed

Contractors

This is an owner-builder project.

  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Anthony R Franks

    Franks & Lane Heating And Air Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Robert Ogles Ii

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

Inspections

  1. Jun 2, 2021

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  2. Jun 2, 2021

    Passed: Building - Footer

    Need Picture Of Grounding Wire

    Inspected by Anthony Aslan

  3. Jun 21, 2021

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  4. Jun 21, 2021

    Release to power company

    Inspected by Anthony Aslan

  5. Jul 20, 2021

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  6. Jul 29, 2021

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Office Plumbing

    Inspected by Anthony Aslan

  7. Aug 10, 2021

    Cancelled: Building - Monolithic Slab

    Inspected by Anthony Aslan

  8. Aug 10, 2021

    Cancelled: Engineering - Setbacks

    Inspected by Anthony Aslan

  9. Aug 10, 2021

    Cancelled: Building - Slab

    Inspected by Anthony Aslan

  10. Aug 11, 2021

    Passed: Building - Monolithic Slab

    Inspected by Anthony Aslan

  11. Aug 11, 2021

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  12. Aug 11, 2021

    Passed: Building - Slab

    Inspected by Anthony Aslan

  13. Sep 3, 2021

    Passed: Building - Roof Decking

    Inspected by Anthony Aslan

  14. Sep 3, 2021

    Passed: Building - Wall Sheathing

    Need Engineer Detail For Garage Front Wall Strapping.

    Inspected by Anthony Aslan

  15. Sep 21, 2021

    Cancelled: Building - Roof Decking

    Inspected by Anthony Aslan

  16. Sep 21, 2021

    Cancelled: Building - Wall Sheathing

    Inspected by Anthony Aslan

  17. Sep 22, 2021

    Passed: Building - Framing

    Windows & Doors Not Installed

    Inspected by Anthony Aslan

  18. Sep 22, 2021

    Cancelled: Building - Wall Sheathing

    Inspected by Anthony Aslan

  19. Sep 22, 2021

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Anthony Aslan

  20. Oct 1, 2021

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  21. Oct 1, 2021

    Passed: Plumbing/Gas - 2nd Rough-In

    Put Pressure On Before Insulation

    Inspected by Troy Crews

  22. Oct 25, 2021

    Passed: Building - Insulation

    Walls Only

    Inspected by Anthony Aslan

  23. Dec 6, 2021

    Passed: Electrical - Permanent Power

    Inspected by Anthony Aslan

  24. Dec 6, 2021

    Release to power company

    Inspected by Anthony Aslan

  25. Dec 21, 2021

    Septic Release Inspection

    Inspected by Health Dept

  26. Mar 3, 2022

    Passed: Building - Final

    Final Termite Spray, Mini Split Needs Control Wire To Condenser In Seal Tight.

    Inspected by Anthony Aslan

  27. Mar 15, 2022

    Certificate-Release Certificate

    Rec'd Corrections

    Inspected by Anthony Aslan