| Passed: Engineering - Setbacks |
|
Anthony Aslan |
4/28/2021 |
| Passed: Building - Footer |
Need Picture Of Grounding Wire |
Anthony Aslan |
4/28/2021 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
5/20/2021 |
| Passed: Building - Slab |
|
Anthony Aslan |
5/26/2021 |
| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
6/2/2021 |
| Release to power company |
|
Anthony Aslan |
6/2/2021 |
| Passed: Building - Lintel/Tie Beam |
|
Anthony Aslan |
6/16/2021 |
| Rescheduled 7/8/2021:Building - Roof Decking |
|
Troy Crews |
7/6/2021 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
7/8/2021 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Anthony Aslan |
8/6/2021 |
| Passed: Building - Framing |
Check Engineering On Truss. |
Anthony Aslan |
8/6/2021 |
| Passed: Building - Insulation |
Tub Needs Water, Some Electrical Things, Some Mechanical Things, Talked To Rodney. |
Anthony Aslan |
8/12/2021 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
8/16/2021 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
8/16/2021 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Anthony Aslan |
8/16/2021 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
8/16/2021 |
| Septic Release Inspection |
|
Health Dept |
8/27/2021 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
9/15/2021 |
| Release to power company |
|
Troy Crews |
9/15/2021 |
| Passed: Building - Final |
|
Anthony Aslan |
10/15/2021 |