Permit Details

Permit Search

Permit

New Residential Construction

371 SW PRIMROSE TERR
FORT WHITE, FL 32038

Permit #
000038554
Application #
42522
Status Completed
  1. Submitted Sep 5, 2019
  2. Issued Sep 5, 2019
  3. Expires Feb 23, 2021
  4. Completed Aug 28, 2020

Property

Parcel #
09621-413
Owner
Gregory Isom
Acres
10.00
Subdivision
Tustenuggee Woods
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0485C
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
900.00
Total Area (Sqft)
1265.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0545

Status & Review History

No status updates yet.

Contractors

  • Jonathan Deans

    License
    CRC1326575
    Title
    —
    Role
    —

    State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Sep 24, 2019

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Sep 24, 2019

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Sep 24, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  4. Sep 24, 2019

    Release to power company

    Inspected by Troy Crews

  5. Oct 30, 2019

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  6. Nov 20, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  7. Dec 17, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. Dec 26, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  9. Feb 13, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  10. Feb 13, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  11. Feb 13, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  12. Mar 3, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  13. Aug 27, 2020

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  14. Aug 27, 2020

    Release to power company

    Inspected by Troy Crews

  15. Aug 27, 2020

    Passed: Building - Final

    Inspected by Troy Crews

  16. Aug 28, 2020

    Certificate-Release Certificate

    Inspected by Troy Crews