Permit Details

Permit Search

Permit

New Residential Construction

388 SW PACES GLN
LAKE CITY, FL 32024

Permit #
000038336
Application #
42164
Status Completed
  1. Submitted Jul 9, 2019
  2. Issued Apr 27, 2021
  3. Expires Oct 24, 2021
  4. Completed May 4, 2021

Property

Parcel #
02431-204
Owner
Aaron Simque
Acres
5.23
Subdivision
West Paces
Zoning
AG-3
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2474.00
Total Area (Sqft)
3964.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0461

Status & Review History

  1. Permit Renewed

Contractors

This is an owner-builder project.

  • Aaron Simque

    License
    R282811879
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jul 30, 2019

    Passed: Building - Footer

    Inspected by Matt Forsyth

  2. Jul 30, 2019

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Aug 21, 2019

    Failed: Plumbing/Gas - Underground Rough-In

    Need Porti Potty. No Plans Or Permit On Site. Vertical Reinforcing Does Not Seem To Be Sufficient. Can Not Verify Because Plans Not On Site.

    Inspected by Tommy Matthews

  4. Aug 23, 2019

    Passed: Electrical - Temporary Service

    Inspected by Tommy Matthews

  5. Aug 23, 2019

    Release to power company

    Inspected by Tommy Matthews

  6. Aug 23, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Tommy Matthews

  7. Aug 23, 2019

    Failed: Building - Slab

    Missing Some Horizontal Reinforcing. Vertical Reinforcing Not As Per Plan. No Porti Potti On Site As Per State Law. $50 Reinspection Fee Before Next Inspection.

    Inspected by Tommy Matthews

  8. Aug 26, 2019

    Passed: Building - Slab

    Inspected by Tommy Matthews

  9. Oct 1, 2019

    Failed: Building - Ext Strapping/Wall Sheathing

    Some Shiners Viable. Walls Not Complete. Need Columns In Place With Strapping To Complete Inspection.

    Inspected by Tommy Matthews

  10. Nov 7, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  11. Jan 7, 2020

    Passed: Building - Framing

    Inspected by Troy Crews

  12. Jan 7, 2020

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Jan 7, 2020

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  14. Jan 7, 2020

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  15. Jan 14, 2020

    Passed: Building - Insulation

    Inspected by Troy Crews

  16. Apr 7, 2020

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Troy Crews

  17. May 29, 2020

    Release to power company

    Inspected by Laurie Hodson

  18. May 29, 2020

    Septic Release Inspection

    Inspected by Health Dept

  19. Aug 12, 2020

    Release to power company

    Inspected by Melissa Garber

  20. May 4, 2021

    Failed: Building - Final

    Need Blower Door Test And Assessment Paid

    Inspected by Matt Forsyth