Permit Details

Permit Search

Permit

New Residential Construction

761 SW SATELLITE LN
LAKE CITY, FL 32025

Permit #
000038187
Application #
40961
Status Completed
  1. Submitted Jun 4, 2019
  2. Issued Jun 4, 2019
  3. Expires May 20, 2020
  4. Completed Nov 27, 2019

Property

Parcel #
00338-001
Owner
Joe & Barbara Royster
Acres
5.00
Subdivision
—
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0270C
This is the construction of a
SFD W/POLE BARN
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2246.00
Total Area (Sqft)
5859.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
19-0410

Status & Review History

No status updates yet.

Contractors

  • W. Stanley Crawford

    License
    RG0042896
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. Jun 10, 2019

    Passed: Building - Footer

    Inspected by Matt Forsyth

  2. Jun 10, 2019

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Jun 10, 2019

    Release to power company

    Inspected by Matt Forsyth

  4. Jun 11, 2019

    Passed: Electrical - Temporary Service

    Inspected by Matt Forsyth

  5. Jun 18, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  6. Jun 19, 2019

    Cancelled: Building - Slab

    Inspected by Matt Forsyth

  7. Jun 24, 2019

    Failed: Building - Slab

    Inspected by Matt Forsyth

  8. Jun 24, 2019

    Passed: Building - Slab

    Inspected by Matt Forsyth

  9. Jul 12, 2019

    Cancelled: Building - Roof Decking

    Inspected by Troy Crews

  10. Jul 12, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Walls On House

    Inspected by Troy Crews

  11. Jul 17, 2019

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  12. Jul 24, 2019

    Passed: Building - Framing

    Porch Beams To Be Nailed 12inch On Center Both Sides

    Inspected by Matt Forsyth

  13. Jul 24, 2019

    Passed: Electrical - Rough In

    Inspected by Matt Forsyth

  14. Jul 24, 2019

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  15. Jul 24, 2019

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Matt Forsyth

  16. Aug 13, 2019

    Passed: Building - Insulation

    Porch Headers Nailed Off Correctly

    Inspected by Matt Forsyth

  17. Oct 4, 2019

    Septic Release Inspection

    Inspected by Health Dept

  18. Oct 10, 2019

    Failed: Electrical - Permanent Power

    Need Door Locks On So We Can Release Permanent Power

    Inspected by Matt Forsyth

  19. Oct 11, 2019

    Passed: Electrical - Permanent Power

    Inspected by Matt Forsyth

  20. Oct 11, 2019

    Release to power company

    Inspected by Matt Forsyth

  21. Nov 22, 2019

    Passed: Building - Final

    Blow Door Test Received 11.27.19

    Inspected by Matt Forsyth