Permit Details

Permit Search

Permit

New Residential Construction

209 SW MARYNIK DR
HIGH SPRINGS, FL 32643

Permit #
000037672
Application #
40182
Status Completed
  1. Submitted Jan 23, 2019
  2. Issued Jan 23, 2019
  3. Expires Feb 19, 2020
  4. Completed Aug 27, 2019

Property

Parcel #
10006-202
Owner
Jason & Jennifer Mueller
Acres
5.00
Subdivision
River Rise
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0513C
This is the construction of a
SFD/UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
2519.00
Total Area (Sqft)
3722.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0971

Status & Review History

No status updates yet.

Contractors

  • Lee A. Holloway

    License
    CGC1510178
    Title
    —
    Role
    —

    County License & State License & Workers Comp Expired.

Inspections

  1. Jan 23, 2019

    Release to power company

    Inspected by Troy Crews

  2. Jan 24, 2019

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  3. Jan 31, 2019

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  4. Feb 5, 2019

    Passed: Building - Slab

    Inspected by Troy Crews

  5. Mar 6, 2019

    Passed: Building - Ext Strapping/Wall Sheathing

    Walls Only

    Inspected by Troy Crews

  6. Mar 19, 2019

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. Mar 27, 2019

    Passed: Building - Framing

    Inspected by Troy Crews

  8. Apr 24, 2019

    Cancelled: Building - Framing

    Inspected by Troy Crews

  9. Apr 25, 2019

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  10. Apr 25, 2019

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  11. Apr 25, 2019

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  12. May 6, 2019

    Passed: Building - Insulation

    Inspected by Troy Crews

  13. Jun 18, 2019

    Passed: Electrical - Permanent Power

    Need Culvert Final And Health Release

    Inspected by Troy Crews

  14. Jun 19, 2019

    Septic Release Inspection

    Inspected by Health Dept

  15. Jun 24, 2019

    Release to power company

    Inspected by Mg

  16. Aug 23, 2019

    Passed: Building - Final

    Inspected by Troy Crews