  1. Submitted May 17, 2018
  2. Issued May 17, 2018
  3. Expires Mar 23, 2019
  4. Completed Sep 24, 2018

Property

Parcel #
02973-114
Owner
Adam's Construction
Acres
0.50
Subdivision
Hunnington Place
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0293D
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1669.00
Total Area (Sqft)
2607.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0392

Status & Review History

No status updates yet.

Contractors

  • Adam Papka

    License
    CBC1253409
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. May 23, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  2. May 23, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. May 23, 2018

    Cancelled: Electrical - Temporary Service

    Inspected by Troy Crews

  4. May 23, 2018

    Passed: Electrical - Footer Steel & Grounding

    Inspected by Troy Crews

  5. May 30, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  6. May 31, 2018

    Release to power company

    Inspected by Troy Crews

  7. Jun 1, 2018

    Passed: Building - Slab

    Inspected by Troy Crews

  8. Jun 1, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  9. Jun 18, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Walls Only No Strapping Roof To Be Done Monday

    Inspected by Troy Crews

  10. Jun 18, 2018

    Passed: Building - Roof Decking

    Inspected by Tommy Matthews

  11. Jul 10, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  12. Jul 10, 2018

    Failed: Building - Framing

    Add Studs Under All Girder Trusses,tempered Glass Needs To Be Moved At Rear Door

    Inspected by Troy Crews

  13. Jul 10, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. Jul 10, 2018

    Passed: Plumbing/Gas - Rough In

    Repair Cut Out Vent And Add Pressure To Water Lines

    Inspected by Troy Crews

  15. Jul 12, 2018

    Failed: Building - Framing

    Items Not Corrected 50$ Reinspection Fee Will Apply

    Inspected by Troy Crews

  16. Jul 12, 2018

    Failed: Plumbing/Gas - Rough In

    Items Not Corrected

    Inspected by Troy Crews

  17. Jul 16, 2018

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  18. Jul 16, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  19. Jul 16, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  20. Aug 29, 2018

    Passed: Electrical - Permanent Power

    Need Health Release & Final On Driveway

    Inspected by Troy Crews

  21. Aug 30, 2018

    Release to power company

    Inspected by Laurie Hodson

  22. Aug 30, 2018

    Septic Release Inspection

    Inspected by Health Dept

  23. Sep 24, 2018

    Failed: Building - Final

    Need Final Termite Certification

    Inspected by Troy Crews

  24. Sep 24, 2018

    Passed: Building - Final

    Inspected by Troy Crews