Permit Details

Permit Search

Permit

New Residential Construction

203 SW PLATEAU GLEN LAKE CITY FL 32024

Permit #
000036406
Application #
36974
Status Completed
  1. Submitted Mar 5, 2018
  2. Issued Mar 5, 2018
  3. Expires Feb 11, 2019
  4. Completed Aug 16, 2018

Property

Parcel #
03113-169
Owner
Stanley Crawford Construction, Inc.
Acres
0.58
Subdivision
Wise Estates
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0381D
This is the construction of a
SFD/UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1630.00
Total Area (Sqft)
2354.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
18-0092

Status & Review History

No status updates yet.

Contractors

  • W. Stanley Crawford

    License
    RG0042896
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. Mar 15, 2018

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Mar 15, 2018

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Mar 15, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  4. Mar 15, 2018

    Release to power company

    Inspected by Troy Crews

  5. Mar 26, 2018

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Troy Crews

  6. Apr 6, 2018

    Passed: Building - Slab

    Inspected by Troy Crews

  7. Apr 6, 2018

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  8. May 1, 2018

    Passed: Building - Roof Decking

    Inspected by Tommy Matthews

  9. May 1, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Tommy Matthews

  10. May 9, 2018

    Failed: Building - Framing

    Need New Set Truss Plans Stamped Set Not Matching House, Check King Studs Large Openings, Bottom Plate Splice In Garage Needs Bolt, King Studs Needed On Garage Header

    Inspected by Troy Crews

  11. May 15, 2018

    Failed: Building - Framing

    Items On Notes Not Corrected Do Not Insulate

    Inspected by Troy Crews

  12. May 15, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  13. May 15, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  14. May 15, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  15. May 16, 2018

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  16. May 16, 2018

    Cancelled: Electrical - Rough In

    Inspected by Troy Crews

  17. May 16, 2018

    Cancelled: Mechanical - Rough In

    Inspected by Troy Crews

  18. May 16, 2018

    Cancelled: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  19. May 18, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  20. Jul 25, 2018

    Septic Release Inspection

    Inspected by Health Dept

  21. Aug 7, 2018

    Passed: Electrical - Permanent Power

    Rec'd All, Need Elevation Confirmation Also Door Locks

    Inspected by Troy Crews

  22. Aug 10, 2018

    Release to power company

    Inspected by Laurie Hodson

  23. Aug 15, 2018

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE

  24. Aug 15, 2018

    Passed: Building - Final

    Blower Door Test Recieved

    Inspected by Troy Crews