Permit Details

Permit Search

Permit

New Residential Construction

213 SW ERIN GLEN LAKE CITY FL 32024

Permit #
000036024
Application #
36209
Status Completed
  1. Submitted Nov 21, 2017
  2. Issued Nov 21, 2017
  3. Expires Jan 9, 2019
  4. Completed Jul 16, 2018

Property

Parcel #
03405-251
Owner
Lacey Developments
Acres
1.11
Subdivision
Southwood Meadows
Zoning
AG-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0383D
This is the construction of a
SFD, UTILITY
Setbacks Front
30.00
Setback Side 1
25.00
Setback Side 2
25.00
Setbacks Rear
25.00
Stories
1
Heated Area (Sqft)
1611.00
Total Area (Sqft)
2249.00
Building Code Edition
Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000)
17-0699

Status & Review History

No status updates yet.

Contractors

  • Adam Papka

    License
    CBC1253409
    Title
    —
    Role
    —

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Dec 12, 2017

    Release to power company

    Inspected by Randy Jones

  2. Dec 12, 2017

    Temporary Power Inspection

    Inspected by Randy Jones

  3. Dec 12, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  4. Dec 12, 2017

    Temporary Power Inspection

    Inspected by Randy Jones

  5. Dec 12, 2017

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  6. Dec 12, 2017

    Passed: Plumbing/Gas - Underground Rough-In

    Inspected by Randy Jones

  7. Dec 12, 2017

    Passed: Electrical - Temporary Service

    Inspected by Randy Jones

  8. Dec 18, 2017

    Slab Inspection

    Inspected by Randy Jones

  9. Dec 18, 2017

    Slab Inspection

    Inspected by Randy Jones

  10. Dec 18, 2017

    Passed: Building - Slab

    Inspected by Randy Jones

  11. Jan 30, 2018

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  12. Feb 23, 2018

    Failed: Building - Framing

    Anchor Bolts Green Paint, Add King Studs Both Sides Rear Window ,garage Door Header Attachment Not Per Plan

    Inspected by Troy Crews

  13. Feb 23, 2018

    Passed: Electrical - Rough In

    Inspected by Troy Crews

  14. Feb 23, 2018

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  15. Feb 23, 2018

    Passed: Plumbing/Gas - Rough In

    Inspected by Troy Crews

  16. Feb 28, 2018

    Passed: Building - Insulation

    Inspected by Troy Crews

  17. Feb 28, 2018

    Passed: Building - Framing

    Items Corrected

    Inspected by Troy Crews

  18. Mar 28, 2018

    Cancelled: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  19. Apr 30, 2018

    Cancelled: Electrical - Underground Rough-In

    Inspected by Troy Crews

  20. Apr 30, 2018

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  21. May 23, 2018

    Release to power company

    Inspected by Laurie Hodson

  22. May 23, 2018

    Septic Release Inspection

    Inspected by Health Dept

  23. Jun 25, 2018

    Failed: Building - Final

    Need Blower Door Test(rec'd 6/28/18), Step In Garage, Faucet In Bathroom

    Inspected by Troy Crews

  24. Jul 13, 2018

    Passed: Building - Final

    Items Corrected

    Inspected by Troy Crews

  25. Jul 16, 2018

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE