Permit Details

Permit Search

Permit

New Residential Construction

249 SW GRANITE CT LAKE CITY FL 32024

Permit #
000033953
Application #
25455
Status Completed
  1. Submitted Apr 12, 2016
  2. Issued Apr 12, 2016
  3. Expires Oct 9, 2016
  4. Completed Nov 23, 2016

Property

Parcel #
03081-207
Owner
Bradley Franks Construction Llc
Acres
0.89
Subdivision
Wingate Estates
Zoning
PRD
Flood zone
X PP
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0380C
This is the construction of a
SFD, UTILITY
Setbacks Front
25.00
Setback Side 1
10.00
Setback Side 2
10.00
Setbacks Rear
15.00
Stories
1
Heated Area (Sqft)
1787.00
Total Area (Sqft)
2514.00
Building Code Edition
Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Septic# (00-0000) or (X00-000)
16-0205

Status & Review History

No status updates yet.

Contractors

  • Bradley Franks

    License
    RG29110384
    Title
    —
    Role
    —

    County License & State License & Workers Comp Expired.

Inspections

  1. Apr 20, 2016

    Foundation Inspection

    Inspected by Troy Crews

  2. Apr 20, 2016

    Setback Inspection

    Inspected by Troy Crews

  3. Apr 27, 2016

    Temporary Power Inspection

    Inspected by Randy Jones

  4. Apr 27, 2016

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  5. Apr 27, 2016

    Temporary Power Inspection

    Inspected by Randy Jones

  6. Apr 27, 2016

    Underslab Rough Plumbing Inspection

    Inspected by Randy Jones

  7. Apr 28, 2016

    Slab Inspection

    Inspected by Troy Crews

  8. May 25, 2016

    Sheeting and Nailing Inspection

    Inspected by Troy Crews

  9. May 25, 2016

    Sheathing and Nailing Inspection

    Inspected by Troy Crews

  10. Jun 13, 2016

    Framing Inspection

    Inspected by Troy Crews

  11. Jun 13, 2016

    Rough-In Plumbing Inspection

    Inspected by Troy Crews

  12. Jun 13, 2016

    Electrical Rough-In Inspection

    Inspected by Troy Crews

  13. Jun 13, 2016

    Heat and Air Duct Inspection

    Inspected by Troy Crews

  14. Jun 24, 2016

    Insulation Inspection

    Inspected by Troy Crews

  15. Nov 4, 2016

    Permanent Power Inspection

    Inspected by Troy Crews

  16. Nov 23, 2016

    Final Inspection

    Inspected by Troy Crews

  17. Nov 23, 2016

    CERTIFICATE OF OCCUPANCY/COMPLETION DATE